Your quote says 300 pieces. A friend says they started with one. Both numbers are real, but they answer different questions.

Bulk MOQ is 300 pcs per style, per color. A sample is one paid piece, not an order. Sampling takes 7–10 days, and bulk production after approval runs 40–60 days.

That is the short answer. What follows is the three numbers behind it, the clocks that start them, and the five lines to put on your quote before you pay.

What Does "300 Pieces per Style, per Color" Actually Mean?

Two words carry all the weight: style and color.

A style is one design — the legging, the tank, the shorts. A color is one shadeway inside that style. Three colors of one legging is a 900-piece commitment, not 300. The same 300 pieces split across two styles leaves neither line at the minimum.

This is the number most first-time buyers underread. The quote line usually says "300 pcs / style / color" and nothing else.

ItemNumberWhat it coversWhat it does not cover
Bulk MOQ300 pcs per style, per colorCutting, sewing, packing slotSamples, extra colors
Paid sample1 pcFit, fabric and construction checkResale, capacity hold
Sample revisions1–2 rounds inside the feePattern tweaks on the same blockA new style or new fabric
Bulk lead time40–60 daysSample approval to packed cartonsFreight, customs, delivery
Stock fabric300–600 m per colorOne dye lot from the mill shelfA custom shade
Custom dyeHigher, quoted per shadeLab dip, then a dye runStock-color speed

If a supplier quotes you a single number without the per-color clause, ask which one they mean. It is usually the style minimum, and it is usually the number that ruins the launch plan.

Is the 1-Piece Sample the Same as an Order?

No. The difference is money and scheduling, not wording.

A sample is one paid unit, made so you can check fit, fabric hand-feel and seam construction before committing. It is quoted at sample cost rather than bulk price, and the fee is normally deducted from the bulk invoice once the order is placed. Ours works that way.

One or two revision rounds usually sit inside that fee. A third round on a new pattern, a new fabric or a new color is quoted separately, because the pattern work restarts rather than adjusts.

20261119-moq-sample-vs-bulk-4x3

A sample also does not reserve production capacity. The sewing slot is booked when the bulk deposit lands, not when the sample ships. Any supplier who promises a ship date at sample stage is quoting a date they do not yet control.

How Long Does Sampling Take?

Seven to 10 days for a standard style. The clock starts when two things are true: the tech pack is approved, and the fabric is confirmed.

Anything built rather than simply cut and sewn adds time. Embroidery and bonding usually add 3–5 days. Custom-dyed fabric adds a lab dip first, then a dyeing window that runs from a few days to two weeks depending on the mill schedule.

StageTypical timeThe clock starts when
Tech pack review1–2 daysTech pack and size chart received
Sample making7–10 daysFabric and color confirmed
Embroidery or bonding+3–5 daysLogo artwork approved
Custom dyeLab dip, then dye windowShade approved on lab dip
Revision roundQuoted per roundComments returned in one batch

The clock is the part buyers misread most often. A tech pack with three open callouts — waistband height, inseam, logo placement — sits in the sample room while everyone waits for one email. Days pass, and the delay gets blamed on the factory.

What Happens Between Sample Approval and Bulk Delivery?

Bulk runs 40–60 days after sample approval for most cut-and-sew programs. The range is honest, not padded. A 300-piece run in stock fabric sits near the short end. Multiple colors, custom dye or heavy logo work sit near the long end.

StageWhen it happensWhat you should receive
Fabric and trims bookedDays 1–10Booking confirmation, PP sample date
Pre-production sampleDays 10–20PP sample for written approval
Cutting and sewingDays 15–45Inline QC notes at agreed checkpoints
Finishing and packingDays 45–60Final inspection report, packing list

Two dates matter more than the total: the PP sample approval date and the final inspection date. Everything in between can absorb a day. Those two move the ship date.

Where Do First Orders Slip?

Most late orders are decided before production starts, not on the line. Three repeat offenders:

  • The fabric is chosen after the sample passes, and the mill has no stock left in that shade.
  • Colors are added one at a time, and each addition reopens the minimum and the dye plan.
  • The logo is approved on a flat drawing instead of on a garment, then reads wrong at scale.

None of these are sewing failures. They are sequencing failures, and each one costs weeks.

What Should You Confirm in Writing Before You Pay?

Five lines, on the quote rather than in a chat thread:

1. Bulk MOQ: 300 pcs per style, per color.

2. Sample: 1 pc, paid, fee deducted from the bulk invoice.

3. Sampling: 7–10 days, plus finishing and dyeing where applicable.

4. Bulk: 40–60 days from written sample approval.

5. Exclusions: freight, duties, third-party inspection.

If a quote offers less than 300, ask what changed. Stock fabric only, fewer colors, or a set-up charge. A number without those conditions is not yet a quote.

Key Takeaways

  • 300 is the bulk minimum per style and per color, and colors multiply it.
  • One piece is a paid sample, priced and scheduled separately from bulk.
  • The 7–10 day and 40–60 day clocks start on approvals, not on enquiry emails.

A sample is a question you pay to ask. Bulk is the answer you commit to.

Buyer FAQ

Can I order one piece and resell it? No. One piece is a paid sample for fit and fabric approval. Resale starts at 300 pcs per style, per color.

Does the sample fee come back? On most programs, and on ours, yes — it is deducted from the bulk invoice. Get the deduction rule written on the quote, not agreed verbally.

Can I split 300 pieces across two colors? Not on one style. The minimum applies per color, so two colors means 600 pieces. Two colors at 150 each will be quoted as a below-MOQ request, if it is quoted at all.

What if I only need 150 pieces? Below-MOQ runs are reviewed case by case and may carry a small set-up charge. Stock fabric and a single color make approval more likely. Ask before you build the launch calendar.

Is 40–60 days including shipping? No. It ends at packed cartons. Ocean freight, customs clearance and inland delivery add their own window on top.

Do you charge for a tech pack review? No. Review is part of quoting. What costs money is the sample itself, and any pattern work that goes beyond adjusting an existing block.

Sources

[1] LAVYSEN internal production handbook, 2026 — MOQ structure, sample rounds, sample-fee deduction, bulk scheduling.

[2] LAVYSEN FAQ — standard MOQ and sampling terms. https://www.lavysen.com/faq/

[3] LAVYSEN case study CASE-04 — a 300-piece first order, cost and timeline. https://www.lavysen.com/case-studies/case-04-latam-small-moq-yoga-shorts/

Request a paid sample (1 pc) and we will confirm fabric, color and the sampling date in writing. https://www.lavysen.com/contact/